Timeline

Project Milestones

  • Business Planning - 109 acres purchased in 1998
  • Begin medical planning and design – August 2011
  • Ceremonial groundbreaking – July 2012
  • Process & workflow planning – January 2013
  • Construction start with site work and footings/foundations – June 2013
  • Deep foundation completed – September 2013
  • Tower cranes arrived – March 2014
  • 1st Steel delivery – June 2014
  • Completion of elevator shaft – August 2014
  • First delivery of precast – October 2014
  • Topping off/completion of steel structure – November 2014
  • Completion of precast – May 2015
  • Opening in 2017